skip to main content

Road Services Division Capital Improvement Program (CIP)

2017-2018 New Guardrail Construction

Project No.:  1131132
Project limits:  Varies
Project type:  Safety
Thomas Bros. Map No.:  N/A

Project description

To design and construct new guardrail systems in 2017-2018.

Why is King County doing this project?

The division's top priority in the 2014 Strategic Plan for Road Services is to address safety concerns on the roadway network. This program will design and construct new guardrail systems to improve the safety of the roadways. Barriers will be installed in an attempt to reduce the number and severity of "run off the road" collisions.
 

Project management phase:  Construction Completed

Status as of May 20, 2019

Construction began on April 23 and was substantially completed on September 20.

 

See also

King County non-emergency phone numbers
Radar Readerboard Program
Signs, signals and crosswalks
Title VI information
Traffic safety in your neighborhood

Adopted Capital Improvement Program & program overview

The Road Services Division Capital Improvement Program (CIP) contains all design and construction and studies for improvements on roads, bridges or transportation facilities in the unincorporated areas of King County.